Govt. Will Close Lagos-Ibadan Expressway From August 3 *see why

Govt. Will Close Lagos-Ibadan Expressway From August 3 *see why

0
863

Despite concerns raised by motorists and other road users, the Federal Government has said there is no going back on the four-month planned partial closure of sections of the Lagos-Ibadan Expressway for reconstruction.

The Federal Controller of Works in Lagos State, Mr Adedamola Kuti, said on Sunday the planned partial closure starting from August 3 would not be postponed even with the next month’s Sallah holiday trips and other religious activities that would increase traffic on the road.

According to him, the aim is to complete that portion of the road before Christmas when the traffic is expected to be heavier.

“What we are doing is to finish the project before Christmas when more people will be travelling. We are not closing the road totally; we are providing routes where people will follow and once everyone is patient, everything will go well,” he said.

The Federal Road Safety Corps had last week notified the public that Julius Berger Nigeria Plc, the construction company handling rehabilitation work on Section 1 of the Lagos-Ibadan Expressway, had given notification of its plan to commence intensive work on the Berger-Kara end of the road on August 3, and would close some sections for four months.

In a telephone interview with one of our correspondents on Sunday, the Ogun Sector Commander of the FRSC, Mr Clement Oladele, said the partial closure of the 1.4 kilometres portion of the road had been postponed before and any further delay would affect its delivery date.

“The project is expected to be delivered by 2021 and any further postponement will affect the date,” he said.

He urged motorists to use alternative routes such as the Lagos-Ota-Itori-Abeokuta and Ikorodu-Sagamu roads during the period.

According to Oladele, palliative work is also ongoing under Ogun River Bridge at the popular Kara Cattle Market to help improve traffic flow.